How’s the progress of the building after the first cut with a blade was taken?
The pace of work is high and the changes are visible every day that goes by. The foundation and the walls will be ready when the boilers arrive on the 14th of May 2007.
  • The BIOAGRO hall is being built as an extension to the existing building.
  • The windows are walled up and the wall is being plastered. The existing wall is now working as a firewall to the future BIOAGRO hall.
  • Excavation och groundwork.
  • Relocation of existing incoming electric cabels.
  • The moulding of the concrete slab for the BIOAGRO hall has begun.
  • The foundation of the chimney and new electric cables for the new boiler room.